Problem 16-17 Given the following information on job times and due dates Job TimeDue Date Job (Hours) (Hours) 3.5 2.0 4.5 6 18 C d 5.0 22 e 2.5 f 6.0 20 a-1. Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time. (3) Earliest due date, and (4) Critical ratio. sequence for First come, first served a-b-c-d-e-f sequence for shortest sd processing time Sequence for Earliest due date Sequence for Critical ratio segcence tor Earliest due b-a-c-f-dmedia%2Faa7%2Faa797bb7-2946-4ebb-b5a2-36Problem 16-17 Given the following information on job times and due dates Job