A product requires two machining operations with a materialhandling step in between. Each machining operation takes 3 minutesto complete (material handling is 2 minutes), and a total of 40products are to be made. What are the completion times and numberof material handli ng operations if the unit load is 1, 4, 8, 10,20. How do these results affect the design of a material handlingsystem?