Below is a table for digging a well Activity Identifier Activity Predecessors Duration (weeks) Clear site Obtain materials Obtain pump Prepare apronA, B Dig well Install pump Train maintainers Run trials C, E F, G Draw the network diagram to represent the project. Identify the critical path for the diagram. Identify the earliest and latest activity times for the project. What is the minimum time needed to complete the project? Explain what it means to crash a project? Use a well known regional or international example of a project to assist you in explaining your point. a. 3 marks 1 mark 8 marks 1 mark b. c. d. e.Below