Course Solutions Uncategorized Q5 Figure 51 Shows Pert Diagram Project Durations Weeks 3 5 11 7 9 15 3 7 11 10 40 2 5 7 3 Q34205956

Q5 Figure 51 Shows Pert Diagram Project Durations Weeks 3 5 11 7 9 15 3 7 11 10 40 2 5 7 3 Q34205956

Hi please answer A,B,C as all relevant to eachother thanks.

Q5. Figure 5.1 shows a PERT diagram for a project with durations in weeks. 3,5,11 7,9,15 3,7,11 10 40 2,5,7 3,8,14 4,6,8 50 80 3,4,9 5,8,13 Figure 5.1 - PERT Chart a) Calculate the expected time and the variance for each task. Expected time [o4m pl6 Variance of activity time [(p o)/6)2 (6 marks) b) For each parallel path, calculate the variance, the standard deviation, the standardized score, the probability of completion of each path in the specified time of 20 weeks, and the probability that all paths will be 