What is the earliest finish time for node A in the diagram below
https://d2vlcm61l7u1fs.cloudfront.net/media%2Fb16%2Fb160af96-ecff-4fa2-af7e-315f33764199%2FphplgUh2o.png
Expert Answer
The earliest time by when the task in node A can be finished is 5 units of time as given in the image.
So it would take 5 units of time for the activity in node A to be completed.