a network consist of the activities in the following list. Times are given in weeks. ES, EF, LS and LF is also given.
a) What is the critical path?
b) what is the total competition time?
https://d2vlcm61l7u1fs.cloudfront.net/media%2F171%2F171de6af-3c73-418f-a9e0-5511a91a3e54%2FphpB9Vh6p.png
Late Early Early Activity Preceding Time Start Finish Late Start Finish 10 15 13 10 15 13 19 19 A B 19 17
Expert Answer
Solution :
Critical Path is ACE with 0 slack.
Project completion time is 19 weeks.